An abandoned mining in Canada’s Yukon will take 40 years and $500 million to properly close, the government estimates. The Faro mine project will undergo a 15-year-construction phase that is expected to cost $30 million per year, and an additional $10 million is thought to be needed for the last 25 years of closure operations.